Table 1 Total cost and multiple of cost of PVIS size and number of PVIS combination

From: A framework for end-of-life photovoltaics distribution routing optimization

PVIS size (kW) Number of trips Overhead cost ($) Mileage cost ($) Weight cost ($) Grand total ($) Number of PVIS Total cost ($) Cost multiplier
1 1 10 6 1 17 100 1660 22x
10 1 10 6 6 22 10 220 3x
100 1 10 6 60 76 1 76 1
3 1 10 6 2 18 100 1780 8x
30 1 10 6 18 34 10 340 1x
300 3 30 18 180 228 1 228 1
5 1 10 6 3 19 100 1900 5x
50 1 10 6 30 46 10 460 1x
500 5 50 30 300 380 1 380 1